An architect designs the building, prepares the drawings and specification, and checks that the design meets the Client's brief and the building regulations. In the UK the title is protected by law, so only someone on the Architects Registration Board register can call themselves an architect.
On many contracts the architect also acts as contract administrator, which is the part that matters to a contractor's cost control.
Worked example
A Main Contractor is building a four-storey residential block for £3,200,000. Halfway through, the architect issues an instruction to change the ground floor entrance from painted render to brick slips. The contractor's QS prices it:
| Item | Amount |
|---|---|
| Omit render and paint, 140 m² | (£4,200) |
| Supply and fix brick slips, 140 m² | £11,900 |
| Extra scaffold, two weeks | £1,300 |
| Net Variation | £9,000 |
The contract sum becomes £3,209,000 once the instruction is valued and agreed. If the contractor does the work without pricing it, the £9,000 comes out of margin.
What the architect's role means in the money
Where the architect is the contract administrator, their instructions and certificates drive the contractor's income. Instructions create variations, certificates confirm what the client must pay, and late or missing drawings can cost the contractor time and money.
Three habits protect margin:
- Log every instruction against the budget line it affects on the day it arrives.
- Price a variation before the work starts, not at Final Account.
- Keep a record of drawing issue dates, so a delay claim can be backed with dates.
Design information is also the main source of cost changes that reach the supply chain. A new drawing revision often means a revised Subcontract order, so the committed cost on the job moves with it.
Related terms
Engineer, Client, Quantity Surveyor (QS), Variation, Main Contractor.
Planyard's variation tracking logs each instruction against its budget line, so the cost of a design change is visible before it reaches the Valuation.