Construction Financial Glossary

Final Account Definition

The final account is the comprehensive financial statement issued at the end of a construction project, summarising all costs, payments, variations, and adjustments. It represents the final agreed amount due between the contractor and the Client.

Worked example

A £850,000 contract is complete. The final account adds £42,300 of agreed variations, deducts £11,800 of omitted work, and takes off £7,500 where a £20,000 Provisional Sum was spent as £12,500. Half of the 3% Retention was released at Practical Completion, so 1.5% of the final sum is still held, and everything else has been paid.

Item£
Original contract sum850,000
Add variations42,300
Less omissions-11,800
Less provisional sum adjustment-7,500
Final account873,000
Paid to date (net of 1.5% retention, £13,095)859,905
Balance, the retention, due as the contract provides13,095

Why Final Accounts Matter in Construction

Final accounts ensure that all contractual obligations have been met and that both parties agree on the total project cost. They provide a clear financial record, resolving any outstanding claims or disputes.

Key Elements of a Final Account

  1. Total project costs, including direct and indirect expenses
  2. Approved variations and omissions
  3. Final adjustments for retention, Credit Notes, or Liquidated Damages

The final account in the CVR

The final account is the end point of the CVR. Until it is agreed, the forecast final value includes variations that may still be argued over, so treat unagreed items with care and do not count them at full value.

Agreeing the account early also clears the way for the retention release. Keep a variations register that is up to date every month, and the final account becomes a matter of adding it up.

In the UK

On JCT contracts the contractor sends the final account documents within a period set in the contract after practical completion.

Under the Standard Building Contract the Quantity Surveyor (QS) then prepares the final adjustment of the contract sum and the Architect issues the final certificate. Under Design and Build the contractor submits a final statement. The exact time limits depend on the contract and its edition, so check the one you are working under.

Variation, Retention, Defect Liability Period, Interim Payment, Valuation, Practical Completion.

Planyard's JCT contract management software keeps variations, retention and payments against each contract, so the figures for the final account are already together.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

Once all work is completed, the snagging list is cleared, and outstanding financial matters are settled.

Live on your first project in hours

You don’t need an ERP rollout to get started. Put one live job in and see its margin while you can still do something about it.