An engineer provides the technical design and checking for part of a building: structure, groundworks and drainage, or mechanical and electrical services. Their calculations and drawings fix quantities and materials, so their decisions are one of the biggest drivers of cost on site. The engineer also confirms, through inspections, that the work is built to the design.
Worked example
A groundworks contractor has a £180,000 Subcontract for foundations on a block of flats. After the trial pits, the structural engineer revises the design and issues a new drawing: strip footings change to deeper trench-fill, and extra reinforcement is added.
| Item | Amount |
|---|---|
| Extra excavation, 85 m³ at £32 | £2,720 |
| Extra concrete, 52 m³ at £128 | £6,656 |
| Extra reinforcement, 3.2 tonnes at £1,150 | £3,680 |
| Extra labour and plant | £1,944 |
| Variation value | £15,000 |
The subcontract becomes £195,000. If the Main Contractor does not raise the variation, the groundworks Subcontractor claims it later and the cost has not been budgeted.
Engineers' changes in the budget
An engineer's revision does not carry a price, so it is up to the contractor to notice the cost. Review each revised drawing for quantity changes, and check whether the change is a Client variation, a design error, or covered by the contract allowances. Keep a drawing register with revision dates so a late revision can be tied to delay and cost.
The engineer can also affect cash. Many contracts require engineer's sign-off before concrete is poured or before a stage payment is released, and inspection delays can hold a Valuation. Allow time for inspections in the programme and the cash flow forecast.
Related terms
Architect, Quantity Surveyor (QS), Variation, Subcontract, Main Contractor.
Planyard's subcontract orders can be revised when a drawing change alters a package, so the committed cost always reflects the latest design.