An engineer provides the technical design and checking for part of a building: structure, groundworks and drainage, or mechanical and electrical services. Their calculations and drawings fix quantities and materials, so their decisions are one of the biggest drivers of cost on site. The engineer also confirms, through inspections, that the work is built to the design.

Worked example

A groundworks contractor has a £180,000 Subcontract for foundations on a block of flats. After the trial pits, the structural engineer revises the design and issues a new drawing: strip footings change to deeper trench-fill, and extra reinforcement is added.

ItemAmount
Extra excavation, 85 m³ at £32£2,720
Extra concrete, 52 m³ at £128£6,656
Extra reinforcement, 3.2 tonnes at £1,150£3,680
Extra labour and plant£1,944
Variation value£15,000

The subcontract becomes £195,000. If the Main Contractor does not raise the variation, the groundworks Subcontractor claims it later and the cost has not been budgeted.

Engineers' changes in the budget

An engineer's revision does not carry a price, so it is up to the contractor to notice the cost. Review each revised drawing for quantity changes, and check whether the change is a Client variation, a design error, or covered by the contract allowances. Keep a drawing register with revision dates so a late revision can be tied to delay and cost.

The engineer can also affect cash. Many contracts require engineer's sign-off before concrete is poured or before a stage payment is released, and inspection delays can hold a Valuation. Allow time for inspections in the programme and the cash flow forecast.

Architect, Quantity Surveyor (QS), Variation, Subcontract, Main Contractor.

Planyard's subcontract orders can be revised when a drawing change alters a package, so the committed cost always reflects the latest design.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

Provides technical design and checking for structure, civil works or building services, and confirms the work is built to the design and to standards.

Live on your first project in hours

You don’t need an ERP rollout to get started. Put one live job in and see its margin while you can still do something about it.