A variation is a change to the work required under a construction contract: an addition, omission or alteration to the scope, quality, sequence or timing, which is valued and added to or deducted from the contract sum. It is the UK term for what US contracts call a change order.
Worked example
A main contract is worth £2,000,000. The Client instructs a re-laid reception and two extra door sets. The QS prices the work at £18,500. The Subcontractor's price for the same work is £11,200, so the contractor earns £7,300 on the variation, and the client also grants a five-day Extension of Time (EOT).
| Line | Amount |
|---|---|
| Variation value to the client | £18,500 |
| Cost, subcontractor variation | (£11,200) |
| Margin on the variation | £7,300 |
The margin is 39% on the variation. Done without agreeing the £18,500, the contractor would carry £11,200 of cost and hope to recover it later.
Variations in the CVR
The CVR should show variations in three tiers, kept apart so the forecast is honest:
| Tier | Amount |
|---|---|
| Original contract sum | £2,000,000 |
| Approved variations | £46,000 |
| Pending variations, not yet agreed | £28,000 |
Only the approved £46,000 belongs in contract value. The £28,000 sits in a separate line, with its cost, until it is agreed. Treat the cost of pending variations as committed from the day the work is instructed, since it is spent whether or not the client pays.
A tidy variations log has one row per variation, with:
- The instruction or request, its date and who gave it.
- The priced value, and the agreed value once settled.
- The matching Subcontract or Supplier cost.
- Any time effect, such as an extension of time.
In the UK
JCT contracts instruct changes through a variation, valued under the contract's Valuation rules. NEC contracts deal with most changes as compensation events, assessed and implemented through quotations. The mechanics differ, but the discipline is the same: notify, price, agree, record.
Related terms
Change Directive, Final Account, Contingency Budget, Valuation, Lump Sum Contract, Quantum Meruit.
Planyard's variation tracking logs each variation against the contract and the matching subcontract or order, so approved and pending values show separately in the CVR.