A variation is a change to the work required under a construction contract: an addition, omission or alteration to the scope, quality, sequence or timing, which is valued and added to or deducted from the contract sum. It is the UK term for what US contracts call a change order.

Worked example

A main contract is worth £2,000,000. The Client instructs a re-laid reception and two extra door sets. The QS prices the work at £18,500. The Subcontractor's price for the same work is £11,200, so the contractor earns £7,300 on the variation, and the client also grants a five-day Extension of Time (EOT).

LineAmount
Variation value to the client£18,500
Cost, subcontractor variation(£11,200)
Margin on the variation£7,300

The margin is 39% on the variation. Done without agreeing the £18,500, the contractor would carry £11,200 of cost and hope to recover it later.

Variations in the CVR

The CVR should show variations in three tiers, kept apart so the forecast is honest:

TierAmount
Original contract sum£2,000,000
Approved variations£46,000
Pending variations, not yet agreed£28,000

Only the approved £46,000 belongs in contract value. The £28,000 sits in a separate line, with its cost, until it is agreed. Treat the cost of pending variations as committed from the day the work is instructed, since it is spent whether or not the client pays.

A tidy variations log has one row per variation, with:

  • The instruction or request, its date and who gave it.
  • The priced value, and the agreed value once settled.
  • The matching Subcontract or Supplier cost.
  • Any time effect, such as an extension of time.

In the UK

JCT contracts instruct changes through a variation, valued under the contract's Valuation rules. NEC contracts deal with most changes as compensation events, assessed and implemented through quotations. The mechanics differ, but the discipline is the same: notify, price, agree, record.

Change Directive, Final Account, Contingency Budget, Valuation, Lump Sum Contract, Quantum Meruit.

Planyard's variation tracking logs each variation against the contract and the matching subcontract or order, so approved and pending values show separately in the CVR.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

An agreed variation changes the contract sum and, normally, the budget for the work it covers. A variation done without agreed pricing adds cost with no matching income, and reduces margin.

Upload your project budget and follow the financial progress in real-time

No credit card required. No sales or IT support needed.