The defect liability period (DLP), more often written defects liability period in the UK, is a set timeframe after a construction project is completed during which the contractor is responsible for repairing any defects that arise. This period is typically outlined in the contract and ensures that any issues due to faulty workmanship or materials are addressed at no additional cost to the Client.
Worked example
A contractor completes a £1.5m building contract with 3% Retention, so £45,000 is held. At Practical Completion half, £22,500, is released and the defect liability period of 12 months starts.
During the period the client reports three defects, and the contractor puts two right. The third, a £3,200 roof leak, is not fixed, so the client has it repaired by others and deducts £3,200 when the remaining retention is due. The contractor receives £19,300.
Why the Defect Liability Period is Important
The DLP provides clients with financial protection, ensuring that contractors fix any issues without requiring additional payment. It also encourages contractors to maintain high-quality workmanship to avoid costly post-completion repairs.
Managing the Defect Liability Period
- Clearly define the DLP duration in the contract, usually ranging from 6 to 24 months
- Keep detailed records of defects reported and remedial actions taken
- Ensure retention funds are properly managed to cover potential repair costs
The defect liability period in the cost report
A completed job still has costs and income to come. Keep a provision in the forecast for putting defects right, and show the retention held by the client as money owed to you, with the date it falls due. Keep the job's cost codes open for the whole period, so call-out costs are charged against the job and not lost in overheads.
In the UK
JCT contracts call it the rectification period, and NEC contracts use the defects date and the defect correction period. Many contracts set 12 months, but the contract states it.
Claims for latent defects can sometimes be made after the period ends, under the contract or under the Limitation Act, so a contractor's exposure may outlast it.
The government plans to ban cash retention in construction contracts, which would change how the period is secured: see Retention.
Related terms
Retention, Retention Bond, Practical Completion, Final Account, Snagging.