Retention is a percentage of each payment that the Client holds back until the work is complete and defects are put right. It is security for the client in case the contractor does not finish or fix defects. In UK contracts it is commonly 3% to 5% of the value of work done, and it is usually released in two stages.

Worked example

A Subcontract is worth £300,000 with 5% retention. Across the job, £15,000 is held back from valuations. At Practical Completion half, £7,500, is released. The remaining £7,500 is released when the 12-month defects period ends and any defects are made good.

EventRetention releasedRetention still held
Final Valuation£0£15,000
Practical completion£7,500£7,500
End of defects period£7,500£0

On a business with £5,000,000 of live work and 5% retention, up to £250,000 of earned money sits with clients at any time. A growing contractor feels that as a cash squeeze.

Retention in the cash flow and WIP

Retention is real income, but not yet cash. Report it separately from the money due now, because it does not arrive when the valuation is paid. Keep two running balances for each job: retention held by the client against you, and retention you hold against each Subcontractor. The first is an asset that comes in late, and the second is a liability you owe back.

Forecast release dates, not only amounts. If practical completion slips by two months, so does half the retention. Retention timing is also why a profitable job can still strain cash: the margin is earned, but part of it is locked up for a year.

Two practical points:

  • Check the retention percentage and release triggers in each subcontract, because they may differ from the main contract.
  • Chase release promptly at practical completion and at the end of the defects period, with defects closed out in writing.

The planned UK ban on retention

In March 2026 the UK government confirmed, in its response to the late payment consultation, that it intends to ban the deduction and withholding of retention under construction contracts. The Small Business Protections (Late Payments) Bill was announced in the King's Speech in May 2026.

RICS does not expect a ban to be in force before 2027, with a transition period of 12 to 24 months likely after that (RICS, Retentions ban proposed).

Until the law changes, retention works as described here. If a contract signed now will run into 2027 or later, check how its defects security would work without cash retention, for example with a Retention Bond.

Retention Bond, Defect Liability Period, Interim Payment, Valuation, Final Account, Practical Completion.

Planyard's subcontractor payment applications calculates retention on each valuation and keeps a running retention balance per subcontract, so you know what you hold and when it falls due.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

In UK practice it is commonly 3% to 5% of the value of work, set in the contract. Some contracts and markets use up to 10%.

Live on your first project in hours

You don’t need an ERP rollout to get started. Put one live job in and see its margin while you can still do something about it.