A project manager (PM) in construction is the person responsible for delivering a job to programme, budget and quality: planning the work, coordinating trades and suppliers, managing the Client relationship and reporting progress and cost. On a contractor's team the PM is also the person most able to move the final margin.
Worked example
A PM runs a £2.4m office fit-out with a 20-week programme. In week 9 the cost report shows the M&E package:
| Item | Amount |
|---|---|
| M&E budget | £210,000 |
| Committed (Subcontract plus orders) | £248,000 |
| Overspend against budget | £38,000 |
The overspend came from a redesigned lighting layout that the client instructed but nobody had priced. The PM asks the QS to price the instruction as a Variation, which recovers £29,000 of it, and finds £4,000 of savings in the remaining ceiling package. Forecast margin on the job falls by £5,000 instead of £38,000.
The PM and cost control
The PM does not need to keep the books, but several cost controls only work if the PM owns them:
- Approve orders and subcontract orders against the budget line before they are placed.
- Instruct work only once a variation is agreed or the commercial risk is accepted knowingly.
- Review the cost report each month for commitments as well as invoices, since an overspend is visible on the order long before the invoice.
- Own the Cost-to-Complete forecast. The PM knows what is left on site better than the accounts team.
- Challenge Subcontractor valuations against progress seen on site.
A PM who sees the numbers once a quarter finds out about the problem once a quarter. A PM who sees committed and forecast cost each month has time to act.
In the UK
On a UK job there can be two project managers: the contractor's, who runs delivery, and the client's, who acts for the employer. Under NEC contracts, "Project Manager" is also a defined role for the person who manages the contract on the client's side. Check which one a document means.
Related terms
Construction Manager, Quantity Surveyor (QS), Client, Cost to Complete.