Project Manager Definition

A project manager (PM) in construction is the person responsible for delivering a job to programme, budget and quality: planning the work, coordinating trades and suppliers, managing the Client relationship and reporting progress and cost. On a contractor's team the PM is also the person most able to move the final margin.

Worked example

A PM runs a £2.4m office fit-out with a 20-week programme. In week 9 the cost report shows the M&E package:

ItemAmount
M&E budget£210,000
Committed (Subcontract plus orders)£248,000
Overspend against budget£38,000

The overspend came from a redesigned lighting layout that the client instructed but nobody had priced. The PM asks the QS to price the instruction as a Variation, which recovers £29,000 of it, and finds £4,000 of savings in the remaining ceiling package. Forecast margin on the job falls by £5,000 instead of £38,000.

The PM and cost control

The PM does not need to keep the books, but several cost controls only work if the PM owns them:

  • Approve orders and subcontract orders against the budget line before they are placed.
  • Instruct work only once a variation is agreed or the commercial risk is accepted knowingly.
  • Review the cost report each month for commitments as well as invoices, since an overspend is visible on the order long before the invoice.
  • Own the Cost-to-Complete forecast. The PM knows what is left on site better than the accounts team.
  • Challenge Subcontractor valuations against progress seen on site.

A PM who sees the numbers once a quarter finds out about the problem once a quarter. A PM who sees committed and forecast cost each month has time to act.

In the UK

On a UK job there can be two project managers: the contractor's, who runs delivery, and the client's, who acts for the employer. Under NEC contracts, "Project Manager" is also a defined role for the person who manages the contract on the client's side. Check which one a document means.

Construction Manager, Quantity Surveyor (QS), Client, Cost to Complete.

Planyard's job costing shows budget, committed and actual cost by Cost Code for each job, so a PM sees an overspend when the order is placed, not when the invoice arrives.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

Plans the work, coordinates trades and suppliers, manages the programme and budget, deals with the client and reports progress and cost. The role varies by company, from running one site to managing several jobs.