The month’s work is done, your subcontractors are waiting on payment, and the G702 is due Friday. Last time, a $25,000 line item was rejected because the retainage calculation did not match the G703 continuation sheet – and the entire pay app sat on the architect’s desk for three weeks. One mistake on the form can stall cash flow for everyone on the project.
This guide walks through every section of the AIA G702 Application & Certificate for Payment with step-by-step instructions, worked examples, and the most common errors that cause rejections. If you are new to AIA billing, start with our AIA billing overview first.
What is an AIA Application for Payment?
An AIA application for payment (commonly known as an AIA pay app) is a standardized payment request document provided by the American Institute of Architects (AIA). This document is widely used in the construction industry because it clearly communicates project financial status and progress. Unlike typical invoices, a pay app requires more detail and certification by the architect or owner before payment is released. Think of the AIA pay app as both a financial report and an invoice. It must precisely reflect what has been earned through the current billing period.
Key Terms Explained
- AIA stands for the American Institute of Architects, which provides standardized forms to facilitate clear and consistent documentation in construction projects.
- AIA G703 Form is the Continuation Sheet, a detailed breakdown supporting the G702 form.
- Pay Application is a formal request for payment submitted periodically (often monthly) documenting completed work, stored materials, and retainage.
- Certificate for Payment refers to the architect’s official certification that authorizes the requested payment.
Step-by-Step Guide: How to Fill Out AIA G702

Part I: Project Information
Clearly provide the following:
- Owner’s name and address
- Contractor’s (your) name and address
- Architect’s name and address (if applicable)
- Project Name, Location, and Project Number
- Application Number (sequential numbering for each billing period)
- Period To: The final day of the current billing cycle
- Contract For: Brief project description and contract signing date
Part II: Contractor’s Application for Payment (Lines 1-9)
Use accurate financial data here:
- Line 1 (Original Contract Sum):
Enter your contract’s original total price.
Example: $600,000 - Line 2 (Net Change by Change Orders):
Total amount of approved change orders to date. Clearly document additions or deductions.
Example: +$20,000 - Line 3 (Contract Sum to Date):
Sum of Line 1 and Line 2.
Example: $600,000 + $20,000 = $620,000 - Line 4 (Total Completed & Stored to Date):
Transfer this number directly from your Continuation Sheet (AIA G703).
Example: $300,000 - Line 5 (Retainage):
Calculate retainage percentage on completed and stored materials as specified in your contract (typically 5-10%).
Example: 10% of $300,000 = $30,000 retainage - Line 6 (Total Earned Less Retainage):
Line 4 minus Line 5.
Example: $300,000 – $30,000 = $270,000 - Line 7 (Less Previous Certificates for Payment):
Total of previous payments received. Enter zero if this is the first pay application.
Example: $100,000 - Line 8 (Current Payment Due):
Line 6 minus Line 7.
Example: $270,000 – $100,000 (previous payments) = $170,000 due now - Line 9 (Balance to Finish, Including Retainage):
Line 3 minus Line 6.
Example: $620,000 – $270,000 = $350,000
Change Order Summary
Clearly summarize all approved change orders (COs):
- Additions and deductions from previous applications.
- Changes approved during the current billing cycle.
- Net amount equals Line 2 above.
Tip: Always confirm every change order is officially approved before inclusion. Unapproved changes can cause disputes and delay payments.
Part III: Sign & Certify
- Contractor’s Certification:
Sign the form in front of a notary public unless explicitly waived by your contract. - Architect’s Certificate:
Do not fill this out – it’s completed by the architect or owner after reviewing your submission.
Common Errors and How to Avoid Them
Avoid these frequent mistakes to streamline payment approval:
- Billing unapproved changes – always secure signed COs first.
- Incorrect retainage calculations – double-check retainage with contract terms.
- Inaccurate calculations – always cross-reference G702 totals with your G703 sheet.
- Missing documentation – attach lien waivers, certified payrolls, and material invoices if required by your contract.
Tip: A single incorrect number – whether it’s a miscalculated total, an outdated retainage amount, or a typo in a payment request – can delay approval and stall payment for weeks or even months. Since AIA billing follows a strict approval process, any discrepancy may require back-and-forth corrections between contractors, architects, and owners.
Example: A subcontractor mistakenly billed an unapproved change order for $25,000. The owner rejected the entire pay application, delaying payment by a month. The solution was implementing strict CO approval processes before billing. Accurate pay applications with documented, approved changes prevent cash flow interruptions and disputes.
What Codes Should Be Used for AIA Construction Billing?
The AIA does not publish its own cost codes. Most contractors use either CSI MasterFormat (commercial) or NAHB cost codes (residential). The key is matching whatever system your architects and owners already expect. For a full comparison of the options, see our guide to AIA construction codes.
How Much Does the AIA G702 Cost?
AIA Contract Documents offers two purchasing options for the G702 form:
- Single-use document: $49.99 – includes unlimited drafts but only one finalized PDF. You have 365 days to edit or finalize, and can work online or in Microsoft Word/Excel.
- Annual subscription: $2,199.99 per user – unlimited access to all 242 AIA documents, including the G703 Continuation Sheet and G701 Change Order form. Includes a clause library, variance checker, and template sharing.
These prices are for the G702 only. The G703 and G701 are priced separately under the single-use option. Check the AIA Contract Documents site for current pricing.
Alternatives to the AIA G702
The AIA G702 is the most widely used pay application form, but it is not the only option. Many projects request AIA-format submissions without requiring contractors to purchase the official form for every payment cycle. As long as your application includes the same information in the same general layout, most GCs and owners will accept it.
Other options include:
- ConsensusDocs forms – a competing set of standardized construction documents developed by a coalition of 40+ industry associations. Their payment application serves the same purpose as the G702/G703 pair.
- Custom Excel templates – many contractors build their own spreadsheets that mirror the G702 layout and auto-calculate retainage, change orders, and balance-to-finish. This avoids per-use licensing fees.
- Construction billing software – platforms like Planyard, Procore, and Sage generate AIA-formatted pay apps automatically from your project data, eliminating manual form filling entirely.
AIA G702 Final Checklist:
- Treat your pay app as a strategic financial document – not just paperwork.
- Always allocate extra time to review and verify your numbers. Never rush at the last minute.
- Clearly document all progress, including photographs or receipts.
- Confirm the exact retainage percentage with the owner or architect.
- Use construction-specific financial software to enhance accuracy and reduce admin time.
Planyard: Simplify AIA Billing with Automation
"A lot of the other subbies have just jumped straight onto it and clicked the link we sent them. They’ve been able to upload their valuations themselves."
Read moreRead how Brown & Bancroft cut CVR time from days to minutes using Planyard.
With Planyard, you can cut down on manual data entry, reduce payment errors, and speed up approvals – ensuring a stress-free billing process for you and your entire team:
- Subcontractors input data digitally – No more chasing paperwork or deciphering messy spreadsheets. Subcontractors enter billing details directly into Planyard’s intuitive system, ensuring consistency and reducing administrative burden.
- Real-time calculations – Say goodbye to costly miscalculations and delays. Planyard automatically verifies figures, applies retainage, and ensures payment requests match contract terms – preventing frustrating back-and-forth corrections.
- Change order tracking – Stay in control of project finances. Approved change orders are instantly updated within the system, so every payment application accurately reflects the latest scope of work – eliminating disputes and preventing overbilling.
- Centralized approvals and transparency – No more lost emails or scattered paperwork. Planyard keeps all pay applications in one place, allowing project managers, owners, and finance teams to review, approve, and track payments in one place. Full visibility into the approval process means fewer delays and a smoother billing cycle.
"We had to get our accountant on board and interface it with Xero, so invoices hit the right job number. Now an invoice gets uploaded in Planyard, I sign it off, and it drops into my Xero payment schedule in three or four weeks – it’s perfect."
Read more
Simplify your pay apps
Planyard automates billing calculations, tracks change orders, and syncs approved costs to your accounting software. Cut days of admin down to hours.