Workforce Burden Rate Definition

The workforce burden rate is the cost of employing a worker on top of their base wage, expressed as a percentage of that wage or folded into a fully burdened hourly rate. It covers employer's National Insurance, pension contributions, insurance such as employer's liability, and paid non-working time such as holiday and sick pay.

Contractors add the burden rate to the base wage before it goes into an estimate or a job cost report, so the labour line reflects what a worker actually costs the business, not just what shows up on their payslip.

A Worked Example

Take a carpenter on a base wage of £30.00 an hour. The figures below are round, illustrative percentages for an example calculation, not a statement of any actual tax or insurance rate:

Cost componentRate (example)Amount
Base wage£30.00
Employer's NI and insurance18% of base£5.40
Pension and paid leave10% of base£3.00
Small tools and consumables2% of base£0.60
Total burden30% of base£9.00
Fully burdened rate£39.00 / hour

At a 30% burden rate, every hour this carpenter works costs the business £39.00, not £30.00. Across a crew and a full project, the gap between the base wage and the burdened rate adds up to a cost that a tender built on base wages alone would miss entirely.

Burden Rate on the Cost Report

Burden is applied before labour hours are costed into a Cost Code, so both the estimate and the job cost report should carry fully burdened rates rather than base wages.

If an estimate is built on base wages and actuals are costed with burden included, every labour-heavy cost code will show an overrun that has nothing to do with productivity on site. It is simply a mismatch in rate basis between the two numbers being compared.

In the UK

In the UK this is usually called labour on-costs or the labour burden. It includes employer's National Insurance, pension contributions, holiday and sick pay, employer's liability insurance and sometimes training.

The percentage varies by business, so calculate your own from payroll and insurance records rather than using a general figure. The same on-costs should be added to the estimate and the cost report.

Workforce burden rate is related to Overhead Costs, Indirect Costs, Billable Rates, and Job Costing.

Planyard's job costing compares labour cost with the budget on each cost code, so when the estimate and the actuals use the same burdened rate, a variance reflects site performance rather than a rate mismatch.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

If a tender leaves burden out of the labour line, the price looks lower than it actually costs to deliver, and the margin on that tender erodes once real payroll costs are factored in.