Construction Financial Glossary

Direct Costs Definition

Direct costs are expenses that can be traced to one specific project, or even one specific Cost Code within it, such as labour, materials, equipment hire and Subcontractor work carried out on that job. They sit opposite Indirect Costs, which support the business as a whole and get spread across several projects rather than charged to one. On a cost report, direct costs are the line items a Project Manager can point to and say exactly which part of the job the money went on.

Worked example

On a £1.2m residential refurbishment, the groundworks package comes in at £85,000 in labour, £40,000 in materials and £15,000 in plant hire, all billed against that one project. Add a £60,000 electrical Subcontract and a £45,000 roofing subcontract, and the direct cost total for those packages alone reaches £245,000. A month later, a groundworks Variation adds another £12,000, and because every cost here carries the same project code, the finance team sees the new total straight away rather than discovering it at the Final Account. None of that changes if the company starts a second project next month, because every pound here is tied to this specific site.

Direct costs in a cost report

In a Cost Value Reconciliation (CVR) or job cost report, direct costs are usually broken down by cost code, labour, materials, plant and subcontractors, so a project manager can compare what was budgeted against what has actually been committed and spent. Indirect costs, such as head office salaries or software subscriptions, sit in a separate section because they do not belong to any single job. Keeping the two apart matters for margin: a project can look profitable on direct costs alone and still lose money once its share of overhead is added in. Forecasting cost to complete also depends on this split, since a reliable forecast only works if direct costs already committed, not just those already paid, are counted every time the report is run.

Indirect Costs, Job Costing, Cost-Plus Contract, Overhead Costs, Cost Breakdown Structure (CBS).

FAQs

How do direct costs differ from indirect costs?

Direct costs can be traced to one project, such as site labour and materials. Indirect costs, such as office rent or admin salaries, support the whole business and get allocated across projects rather than charged to a single job.

Are subcontractor payments a direct cost?

Yes. Payments to a subcontractor for work carried out on a specific project are a direct cost, because they can be tied to that job rather than spread across the business.

Planyard tracks direct costs against cost codes in real time through its job costing feature, so budgeted and actual figures stay visible without a spreadsheet reconciliation at month end.

Upload your project budget and follow the financial progress in real-time

No credit card required. No sales or IT support needed.