A cost breakdown structure (CBS) is a hierarchy that sorts every cost on a project into levels, from broad headings such as substructure or mechanical down to individual items of labour, materials and Subcontract. It is the framework the budget, orders and invoices are all measured against. A project with a clear CBS can say where each pound went.
Worked example
A £1,200,000 office fit-out is organised in three levels. Level 1 is the trade package, level 2 is the type of cost.
| Level 1 | Level 2 | Budget |
|---|---|---|
| Partitions and ceilings | Subcontract | £190,000 |
| Partitions and ceilings | Materials supplied | £35,000 |
| Mechanical and electrical | Subcontract | £360,000 |
| Joinery and finishes | Subcontract | £240,000 |
| Preliminaries | Site team and welfare | £150,000 |
| Contingency | £45,000 | |
| Total budget | £1,020,000 |
The budget of £1,020,000 against a £1,200,000 contract leaves a planned margin of £180,000, or 15%. Because every line has a place in the structure, a £25,000 overspend on mechanical shows up against that one line and not as a vague overspend on the job.
A CBS in the CVR and forecast
The CVR needs the same structure on both sides: the value earned for each package and the cost incurred against it. If the CBS used by the estimator differs from the one used by the accounts team, comparing the two means a spreadsheet of mappings and a monthly argument.
- Keep the structure to three levels for most jobs. More detail makes coding slower and rarely improves control.
- Use the same structure on every job so reports can be compared across the business.
- Put contingency in its own line so draw-down is visible.
- Give every line a Cost Code and use that code on orders and invoices.
The CBS is also where cost to complete is forecast. Each line gets a forecast final cost, which is the actual to date plus commitments plus the estimate of what is still to buy.
Related terms
Cost Code, Work Package Costing, Direct Costs, Project Cost Breakdown, Indirect Costs.
Planyard's budget software holds the cost structure for each job, so orders and invoices are tracked against the same lines as the budget.