Construction Financial Glossary

Change Directive Definition

A change directive is a written instruction from the owner or their representative to carry out a change to the work immediately, with the price and time impact agreed afterwards. It is a US form (it appears in the AIA documents), and its purpose is to stop the job waiting while the parties agree the numbers.

Worked example

A tenant asks for extra wall-mounted power and data points in a fit-out. The Client's representative issues a directive on a Monday and the work starts on Tuesday, before any price is agreed. The contractor records its costs from the first hour:

ItemAmount
Electrician, 34 hours at £38£1,292
Cable, trunking and accessories£860
Supervision, 4 hours at £45£180
Cost£2,332
Overhead and profit at 15%£350
Valuation of directive£2,682

If the contractor had not kept the record, the client could challenge the hours weeks later and the contractor would have no proof of what the change cost.

Tracking an open directive in the cost report

Until the price is agreed, the directive is an unvalued Variation. Costs are going out, income has not yet been confirmed and the CVR will show a loss on that line. Add the directive to the cost report with an estimate of its value so the position is visible, and mark it as unagreed.

Chase the price quickly. The longer the gap between doing the work and agreeing the sum, the harder it is to evidence. Include the directive in the next valuation on a stated basis, as work done under an instruction.

In the UK

UK contracts do not usually use the term. Under JCT the contract administrator issues an instruction, and the variation is then valued under the contract rules. Under NEC the Project Manager instructs a change and the contractor submits a quotation for a Compensation Event. The idea is the same: work can start before the cost is finalised, and the record you keep matters.

Variation, Valuation, Final Account, Time and Materials (T&M) Contract, Compensation Event.

Planyard's variation tracking records each instruction against its budget line, so an unpriced change is on the cost report from the day the work starts.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

A change directive is a written instruction from the owner or their representative to carry out a change in the work immediately, with the price and time effect agreed afterwards.

Upload your project budget and follow the financial progress in real-time

No credit card required. No sales or IT support needed.