A billable rate is the hourly or unit price a contractor, Subcontractor or consultant charges for labour, plant or services, set to cover the cost of the resource plus overhead and profit. On time and materials work and daywork, the rate is the price. If it is set too low, every hour worked loses money.
Worked example
A subcontractor employs a joiner paid £22 an hour. The charge-out rate is built up like this:
| Element | Per hour |
|---|---|
| Wage | £22.00 |
| Employer on-costs (NI, pension, holiday), say 25% | £5.50 |
| Tools, van and supervision | £4.50 |
| Cost per paid hour | £32.00 |
Not every paid hour can be charged. If 85% of hours are billable, the cost per billable hour is £32.00 ÷ 0.85, which is £37.65. Adding 15% for overhead and profit gives a rate of about £43.30 an hour. Charging £35 an hour, the wage plus a little, would feel profitable and still lose money.
Billable rates in the job cost report
Compare the rate to what the labour actually costs the job. If the cost report shows 400 joiner hours at £32 paid cost, that is £12,800. Billed at £43.30, the income is £17,320, a gross margin of £4,520. When the margin is lower than the rate suggests, the usual culprits are unbilled hours, travel time and rework.
Review rates at least once a year, and whenever wages or National Insurance change. Make sure the rate card used for variations and daywork matches the rate used internally, or the two will disagree at Final Account. For subcontractors on CIS, remember that the deduction is a tax payment on account and does not change the rate.
Related terms
Time and Materials (T&M) Contract, Cost-Plus Contract, Workforce Burden Rate, Overhead Costs, Markup.
Planyard's job costing tracks labour cost against the budget on each job, so the real cost behind a billable rate is visible rather than assumed.