Work-in-Progress (WIP) Report Definition

A work-in-progress (WIP) report, or WIP schedule, is a summary of every live contract showing its contract value, forecast cost, cost to date, percentage complete, value earned, amount billed and the over or Underbilling. It gives directors, accountants and lenders a single view of how much profit is earned and how much cash is ahead of or behind the work.

Worked example

JobContractForecast costCost to dateCompleteEarnedBilledOver / (under)
A£1,200,000£1,000,000£600,00060%£720,000£760,000£40,000
B£800,000£680,000£340,00050%£400,000£360,000(£40,000)
C£500,000£420,000£252,00060%£300,000£300,000£0

The net figure is zero, which looks fine, but Job A is overbilled £40,000 and Job B is underbilled £40,000. Cash from A is paying for work that is still to be done on A, while B's work is not yet claimed. The report shows what a single total would hide.

Reading and trusting the report

Percentage complete here is cost to date over forecast cost, so everything depends on the forecast cost. If Job A's forecast cost is understated, its percentage complete is too high, the earned value is too high and the profit looks better than it is. A WIP report is only as good as the Cost-to-Complete estimate behind it.

Check each month:

  • That cost to date includes accruals for work done and not yet invoiced.
  • That the forecast cost has been updated for this month's orders and variations.
  • That large overbillings are intended, for example a deliberate early billing agreed with the Client, not an error.
  • That forecast profit on each job moves for a reason you can explain.

Accountants use the WIP schedule to set revenue and profit in the year-end accounts, and banks and sureties often ask for it. Having it ready each month, from the same data as the job reports, avoids a year-end scramble.

Overbilling, Underbilling, Progress Billing, Cost to Complete, Cost Value Reconciliation (CVR).

Planyard's cost value reconciliation holds valuations, cost and forecast cost to complete for each job, which gives the figures a WIP report needs without a separate spreadsheet.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

Monthly, aligned with your cost reporting and valuation cycle. Quarterly is too slow for most contractors, and the report is also needed at year end and when a bank or surety asks.