Construction Financial Glossary

Value Engineering Definition

Value engineering is a structured review of a project's design, materials, and construction methods, carried out to find a way to deliver the same function at a lower cost, or more function at the same cost.

It is built around the ratio of function to cost, so a change only counts as value engineering if it protects or improves performance. A change that simply strips out scope or quality is a cost cut, not value engineering.

The review is usually run as a workshop with the designer, the Quantity Surveyor (QS) or estimator, and the contractor each looking at the same line item from a different angle.

A Worked Example

An Architect specifies natural stone paving for the external works at £180 per square metre across 2,000 square metres, for a total of £360,000. During a value engineering review, the team proposes a concrete paver that meets the same slip resistance and load rating, priced at £140 per square metre, for £280,000, a saving of £80,000 on that one package.

Because the substitute meets the original performance specification rather than lowering it, the change qualifies as value engineering rather than a scope cut.

Value engineering is most common on projects with a fixed or capped budget, where a Target Cost Contract leaves little room to absorb a design that has come in over estimate.

Value Engineering on the Budget

A value engineering saving is logged against the Cost Code it affects, usually as an omission, a negative Variation, or a reforecast of that line item, so the budget reflects the lower committed cost rather than the original estimate. On a cost report, that normally shows up as the original budget, a note referencing the value engineering item, and the adjusted forecast sitting below it.

In the UK

Since the Grenfell Tower fire, value engineering has been criticised where it was used as cover for swapping in cheaper products that performed worse.

Any substitution that affects fire or structural safety needs the designer's sign-off, and on higher-risk buildings under the Building Safety Act 2022 a change to the approved design has to go through the change control process before the work is done. For a contractor, an agreed saving is recorded as a variation, and who keeps it depends on the contract.

Value engineering is closely tied to Cost Breakdown Structure (CBS), Variation, Allowance, and Contingency Budget.

When a value engineering saving is agreed, Planyard's variation tracking records it as a change against the budget line it affects, so the lower committed cost and the reason stay on the project record.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

It works best during design, before drawings are locked and materials are ordered, though teams sometimes run a value engineering pass later if quotes come back too high or a material becomes hard to source.