Construction Financial Glossary

Unit Cost Estimate Definition

A unit cost estimate prices construction work by multiplying a cost per unit of measurement, such as £ per square metre, per metre or per hour, by the quantity of work. It is the working method behind most estimates and bills of quantities, and it makes quantities easy to change.

Worked example

A fit-out estimator builds a rate of £48 per m² for stud partitions:

Element of the rate£ per m²
Labour£22
Materials£19
Plant and consumables£2
Overheads and profit£5
Rate£48

The job has 1,200 m² of partitions and 300 m² of floor tiling at £62 per m². The estimate is 1,200 × £48 = £57,600, plus 300 × £62 = £18,600, a total of £76,200.

Unit costs in the budget and cost report

Unit rates are more useful after the estimate than before. Carry them into the budget so each line has a quantity and a rate, then compare real cost with the rate at the end of each job. If the partitions cost £52 per m² in the end, the variance is 1,200 × £4 = £4,800, and the next estimate should use £52 or a clear reason for £48.

Keep your own database of actual rates:

  • Record the quantity and final cost for each package at the end of the job.
  • Note what drove the difference, such as access, working hours or a Supplier price change.
  • Index old rates for inflation before reusing them, and adjust for job size and complexity.

A rate built from last year's market is a guess this year, so date every rate. Where a rate is used on a measured contract, remember the Client pays by measured quantity, so a rate that is too low costs money on every unit.

Bill of Quantities (BoQ), Unit Price Contract, Job Costing, Cost Code, Lump Sum Contract.

Planyard's construction budgets let you build a job budget by Cost Code with quantities and rates, then compare actual and committed cost against each line as the job runs.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

A unit cost estimate gives a price per measured unit and multiplies by quantity. A lump sum estimate gives one total price for the whole scope, with no per-unit rate shown.

Live on your first project in hours

You don’t need an ERP rollout to get started. Put one live job in and see its margin while you can still do something about it.