Construction Financial Glossary

Material Price Escalation Clause Definition

A material price Escalation Clause is a contract term that adjusts the price when the cost of named materials moves beyond an agreed threshold, so the risk of market swings is shared instead of sitting entirely with the contractor.

In UK contracts it is usually called a fluctuations clause. It matters most on long programmes, where steel, copper or timber can move a long way between tender and purchase.

Worked example

A contractor tenders a £1,200,000 frame and envelope package. The price allows £240,000 for 240 tonnes of structural steel at a base price of £1,000 a tonne. The clause adjusts the price for any rise above 5% of the base, measured against a published index. By the time the steel is ordered, the price is £1,150 a tonne, up 15%.

The adjustment covers the part of the rise above the threshold: £1,150 less £1,050 is £100 a tonne, so 240 × £100 = £24,000. The first 5% (£12,000) stays with the contractor. Without the clause the contractor would absorb the full £36,000, which is 3% of the contract sum.

Escalation in the budget and CVR

Budget the steel at the tender price and record the base price and quantity on the cost line. When the order is placed at the higher price, the committed cost shows the overspend straight away, before any invoice arrives.

If the clause allows recovery, the £24,000 is a claim on the Client, so it goes into the CVR as a pending adjustment to contract value, separate from approved income until it is agreed. With no clause, the full £36,000 comes out of forecast margin.

Three terms decide whether you recover the money:

  • Which materials are covered. A clause that names only steel does not help with a copper spike.
  • How the movement is measured: a published index, Supplier quotations or invoices.
  • The cut-off. Many clauses stop adjusting the price once the work is late through the contractor's own delay.

In the UK

JCT fixed-price contracts have fluctuations options that the parties select in the contract particulars: one for changes in taxes and levies, one for changes in labour and material costs, and a formula-adjustment option. NEC contracts offer a price adjustment for inflation option. If the contract is silent, the price is fixed and the contractor carries the movement.

Escalation Clause, Cost Escalation, Lump Sum Contract, Contingency Budget.

Planyard's construction forecasting compares committed costs on purchase orders with the budget, so a price rise on an order shows in the Cost-to-Complete forecast as soon as the order is placed.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

On long programmes, or where a large share of the price is a few volatile materials such as steel, copper or timber. On a short job with materials bought at the start, the clause adds paperwork for little protection.

Live on your first project in hours

You don’t need an ERP rollout to get started. Put one live job in and see its margin while you can still do something about it.