General conditions are the costs of running and supervising a construction site that aren't tied to any single trade, such as a site manager's salary, temporary power and water, site offices, and project insurance.
They sit apart from the direct cost of labour and materials in a budget, but they are a real project cost, usually priced as their own line item or a percentage of contract value in a bid.
Two related meanings
The term covers two related things. As a cost category, it means the site overhead described above. As a contract term, "General Conditions of the Contract for Construction" is also the title of AIA Document A201.
That is the standard set of boilerplate terms many US construction contracts use for how changes, payments and disputes are handled. The two share a name because site overhead was traditionally described in that section of the contract.
A worked example
A £3 million commercial fit-out budgets general conditions at 8% of contract value, or £240,000. That covers a site manager for 10 months at £12,000 a month (£120,000), a site office with temporary power and water at £60,000, contract works insurance at £30,000, and site administration at £30,000.
A two-month programme extension then adds two more months of site manager cost (£24,000) and site office cost (£12,000). Actual general conditions spend rises to about £276,000, a £36,000 overrun that lands on this line rather than on any single trade's cost.
Where general conditions show up in a budget
General conditions are usually set up as their own Cost Code or group of codes in the budget, separate from labour and material costs, so site overhead can be tracked and reported on its own.
Because much of it is time-based rather than tied to a quantity of work, a delay to the programme shows up directly as a general conditions overrun, which is one reason it's worth watching alongside the schedule.
In the UK
In UK practice the site-running costs are called preliminaries, or prelims, and are priced in their own section of the tender or Bill of Quantities (BoQ). UK contracts also have "conditions" meaning the contract terms, such as the JCT or NEC conditions, so "general conditions" is rarely used for site overhead. If you are reading a US document, read general conditions as the preliminaries.
Related terms: Indirect Costs, Lump Sum Contract, Mobilization Cost, Preliminary Costs.