Draw Request Definition

A draw request is a formal document submitted by a contractor to request payment for work completed during a specific phase of a construction project. It details the percentage of work completed, associated costs, and supporting documentation for verification.

Worked example

A £2,000,000 build is funded by a lender. At the third draw, the work completed to date is certified at £730,000, which is 36.5% of the contract. The lender holds 5% retainage, and £420,000 was released in the first two draws.

Item£
Work completed to date730,000
Less retainage (5%)-36,500
Less previous draws-420,000
This draw273,500

How Draw Requests Work

Draw requests are used in Progress Billing structures where payments are made in instalments. The contractor submits a draw request to the project owner or lender, who reviews and approves the request before funds are released.

Best Practices for Submitting Draw Requests

Ensure all required documentation, such as invoices and progress photos, is included

Align draw requests with the project schedule and percentage of completion

Communicate with project stakeholders to prevent payment delays

Draw requests in the cash flow

A draw is paid only after review, so the contractor funds the work until the money arrives. Build the lender's review time into the cash flow forecast, and submit the request as soon as the Valuation is agreed.

Late supporting documents, such as invoices or inspection sign-off, are the usual cause of delay. In the CVR the work is valued when it is done, with the draw not yet received shown as money owed.

In the UK

Draw request is a US term, and UK contractors say application for payment or interim valuation, usually monthly. The nearest UK idea to the lender's draw is a development loan drawdown, which a lender's monitoring surveyor often certifies before the funds are released.

Progress Billing, Retention, Schedule of Values, Payment Application, Interim Payment, Lien Waiver, Owner Financing.

Planyard's JCT payment application software tracks each application against the contract sum, variations and Retention, so the amount you request matches the work done.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

Typically monthly or upon reaching significant project milestones.

Live on your first project in hours

You don’t need an ERP rollout to get started. Put one live job in and see its margin while you can still do something about it.