Back charges are deductions made by a Main Contractor from a Subcontractor’s payment due to costs incurred from the subcontractor’s failure to meet contract requirements. These can result from defective work, missed deadlines, or additional labour required to fix issues.
Worked example
A subcontractor's Valuation is £40,000 gross. The main contractor holds 5% Retention (£2,000) and has paid £20,000 at earlier valuations. The subcontractor left plaster damage that the main contractor had repaired for £1,800, and a skip it should have cleared cost £550. The back charge is £2,350.
| Item | £ |
|---|---|
| Gross valuation | 40,000 |
| Less retention (5%) | -2,000 |
| Less paid previously | -20,000 |
| Less back charge | -2,350 |
| Payment due | 15,650 |
How Back Charges Affect Project Costs
Back charges directly impact a subcontractor’s earnings, reducing their final payment amount. They are commonly used to recover costs for rework, equipment rental, or corrective measures needed to keep a project on schedule.
Preventing and Managing Back Charges
To avoid disputes, subcontractors should carefully document their work, address deficiencies proactively, and maintain clear communication with the main contractor. Contracts should outline clear guidelines for back charges to prevent unexpected deductions.
Back charges in the cost report
Record the back charge against the Subcontract package it relates to, so the package cost shows the net amount. Do not book it as income. Keep the evidence with it: the instruction, photos, and the invoices for the remedial work. Without that, a subcontractor can dispute the deduction, and the cash stays on the contractor's cost side until it is settled.
In the UK
UK contracts often call these contra-charges or set-off. Under the Construction Act, a payer that wants to pay less than the notified sum generally has to give a valid Pay Less Notice in time, so a back charge added after that date may not hold. Check the subcontract terms, and give the subcontractor early written notice of the issue.
Related terms
Subcontract, Retention, Liquidated Damages, Variation, Contra Charge.
Planyard's subcontractor valuations puts each valuation, retention and deduction against the subcontract order, so a back charge is visible at the point you pay.