Advance billing is invoicing the Client for part of the contract sum before the work or materials are delivered. Contractors use it to fund mobilisation, Supplier deposits and long-lead items, so they are not financing the start of the job from their own bank account. It only works where the contract provides for it.
Worked example
A fit-out contract is worth £600,000. The contract allows a 10% advance, so the contractor invoices £60,000 in week one. Before the first Valuation the contractor has to pay £45,000 as a deposit on bespoke joinery and £15,000 for site set-up, a total of £60,000. Without the advance, the first valuation would not be paid for around six weeks.
The client recovers the advance by deducting 20% from each valuation until it is repaid.
| Valuation | Gross value | Advance recovered | Advance still to recover |
|---|---|---|---|
| Start | £0 | £0 | £60,000 |
| 1 | £100,000 | £20,000 | £40,000 |
| 2 | £100,000 | £20,000 | £20,000 |
| 3 | £100,000 | £20,000 | £0 |
Advance billing in the cash flow and CVR
An advance is cash, not value earned. If it is booked as turnover on day one, the job looks profitable before any work is done and the margin will fall back later as the advance is recovered. Keep it separate: value earned comes from the valuation, and the advance sits as a payment on account until the deductions clear it.
In the cash flow forecast, the advance lifts cash in week one and then reduces every valuation payment until the third valuation. That is a timing gain, not extra money. A forecast that ignores the deductions will show a cash dip that was already planned for. The same care applies to Overbilling, where cash received runs ahead of value earned on the CVR.
Agree the terms in the contract: the percentage, when it is invoiced, how it is recovered and whether the client wants security such as an advance payment bond.