Valuation is the assessment of completed work used to determine interim payments throughout a construction project. It ensures that contractors are compensated for the work completed at regular intervals, based on agreed-upon schedules.
Worked example
At the fourth monthly valuation, work done is £240,000, including £18,000 of materials on site. Variations add £12,000, so the gross valuation is £252,000. Retention at 3% is £7,560, leaving £244,440. Earlier payments total £186,000, so the amount due this month is £58,440.
| Item | £ |
|---|---|
| Work done and materials on site | 240,000 |
| Add variations | 12,000 |
| Gross valuation | 252,000 |
| Less retention (3%) | -7,560 |
| Less paid previously | -186,000 |
| Amount due | 58,440 |
How Valuation Affects Interim Payments
Valuation provides a fair assessment of the work completed, allowing contractors to receive payments at key milestones. This process helps manage cash flow and ensures that contractors are paid for progress made, rather than waiting for full project completion.
Best Practices for Valuations
Contractors should ensure that the valuation process is transparent and accurately reflects the work completed. Regular site inspections and thorough documentation of progress can ensure accurate valuations. Contractors should also agree on a clear valuation schedule with clients at the start of the project.
Valuations in the CVR
The valuation is the value side of the CVR: what has been earned, set against what it has cost. A contractor values its own work for its Client, and also values each Subcontractor's work, so the CVR compares the client's valuation (income) with the Subcontract valuations and other costs. Work done but not yet certified should be added in, with care, so that value is not understated.
In the UK
Valuation also has other meanings, such as a property valuation. In construction payments it is the interim assessment of the work done, made in response to the contractor's application for payment. Under the Construction Act, the payer issues a Payment Notice, and if it wants to pay less than the notified sum, it must serve a Pay Less Notice in time. A QS usually carries out the valuation.
Related terms
Interim Payment, Payment Application, Retention, Variation, Progress Billing.