A bill of quantities (BoQ) is a document that lists the items of work in a project with the measured quantity of each, so every tenderer prices the same thing. It is usually prepared by a Quantity Surveyor (QS) from the drawings and specification, often using the RICS New Rules of Measurement (NRM2). Once priced, it becomes a ready-made schedule for valuations and for valuing changes.
Worked example
A small extension is tendered on a BoQ. The contractor adds rates to each measured quantity:
| Item | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Excavate foundations | 60 | m³ | £38 | £2,280 |
| Concrete foundations | 24 | m³ | £145 | £3,480 |
| Facing brickwork | 95 | m² | £92 | £8,740 |
| Roof covering | 48 | m² | £105 | £5,040 |
| Total | £19,540 |
If the contract is remeasurable and the site is dug to 72 m³ rather than 60, the contractor is paid 12 extra m³ at £38, which is £456. On a Lump Sum Contract without quantities the same overrun would be the contractor's problem. Where the bill is itself a contract document, as under JCT With Quantities, an error in the billed quantity is corrected and valued as a Variation.
Turning a BoQ into a budget and valuations
The priced BoQ is the sell side of the job. The contractor's budget is different: it holds the cost the contractor expects to pay for labour, materials and subcontractors against the same items. Keeping the two side by side is what lets you see the margin on each item. In the example above, brickwork sells at £8,740 but may be budgeted at £7,100 once Subcontract prices are in, a margin of £1,640.
Each month the Valuation is built from the BoQ items, with the percentage complete applied to each line. Variations are valued from the same rates, which is a good reason to keep the rates fair at tender. Update the BoQ budget when instructions change quantities, otherwise the CVR drifts away from what is actually being built.