Construction Financial Glossary

Bill of Quantities (BoQ) Definition

A bill of quantities (BoQ) is a document that lists the items of work in a project with the measured quantity of each, so every tenderer prices the same thing. It is usually prepared by a Quantity Surveyor (QS) from the drawings and specification, often using the RICS New Rules of Measurement (NRM2). Once priced, it becomes a ready-made schedule for valuations and for valuing changes.

Worked example

A small extension is tendered on a BoQ. The contractor adds rates to each measured quantity:

ItemQtyUnitRateAmount
Excavate foundations60m³£38£2,280
Concrete foundations24m³£145£3,480
Facing brickwork95m²£92£8,740
Roof covering48m²£105£5,040
Total£19,540

If the contract is remeasurable and the site is dug to 72 m³ rather than 60, the contractor is paid 12 extra m³ at £38, which is £456. On a Lump Sum Contract without quantities the same overrun would be the contractor's problem. Where the bill is itself a contract document, as under JCT With Quantities, an error in the billed quantity is corrected and valued as a Variation.

Turning a BoQ into a budget and valuations

The priced BoQ is the sell side of the job. The contractor's budget is different: it holds the cost the contractor expects to pay for labour, materials and subcontractors against the same items. Keeping the two side by side is what lets you see the margin on each item. In the example above, brickwork sells at £8,740 but may be budgeted at £7,100 once Subcontract prices are in, a margin of £1,640.

Each month the Valuation is built from the BoQ items, with the percentage complete applied to each line. Variations are valued from the same rates, which is a good reason to keep the rates fair at tender. Update the BoQ budget when instructions change quantities, otherwise the CVR drifts away from what is actually being built.

Lump Sum Contract, Unit Price Contract, Quantity Surveyor (QS), Valuation, Variation.

Planyard's budget software lets contractors split a job into the same items as the BoQ, so each line can be tracked against its cost.

Frequently asked questions

We've got your questions covered. If you can't find the answer below, then feel free to contact us via the chat.

A BoQ lets every tenderer price the same measured quantities, so bids can be compared fairly. After award the priced BoQ often forms the basis for valuations and for valuing variations.

Upload your project budget and follow the financial progress in real-time

No credit card required. No sales or IT support needed.